The concrete structure is
complete. Installation of the perimeter framing, sheathing, insulation and
weather barrier has started and is 60% complete. Brick work will start by
November 6th. Mechanical rough in has started in the interior of the
building.
1619 Chicago Avenue
Updates for the construction work being performed at 1619 Chicago Avenue in Evanston, Illinois.
Thursday, October 29, 2015
Thursday, June 11, 2015
Update June 11, 2015
All deep grade beams and
basement foundations are complete. The shallow east side grade beams are
complete with 8 first floor columns. The shallow west side grade beams will
start week of 6/15/15. There will be no revisions to the construction
barricades in the near future.
Wednesday, March 25, 2015
Update March 25, 2015
The caissons, sheeting and excavation for the basement are complete. Concrete began being poured the week of March 23rd. The basement foundations and grade beams will be worked on for the next few months.
Wednesday, November 19, 2014
Update November 19, 2014
Site Demolition work is complete. Foundation and Caisson will begin this week and continue through mid December.
Monday, October 27, 2014
Update October 27, 2014
Installation of temporary fencing around the perimeter of the
construction site will commence the week of October 27th followed by
minor site demolition, earth retention, and foundation construction. The site
will be set up using the East traffic lane, curb lane and sidewalk in front of
the property for both site access and a pedestrian walkway to maintain
pedestrian traffic along the East side of Chicago Avenue during the duration of
the construction project. Site
demolition and foundation work will commence in early November and will
continue through December 2014.
Wednesday, October 8, 2014
Project Contacts
Valenti Builders
Project Executive, Bob Weber, ph: (847) 716-7226, email: bob.weber@valentibuilders.com
Project Superintendent, Fran Giuffre, fran.giuffre@valentibuilders.com
City of Evanston
Evanston 311
Division of Engineering, Pelayo Enerio Jr. (Jhun), ph: (847) 448-4311
Project Executive, Bob Weber, ph: (847) 716-7226, email: bob.weber@valentibuilders.com
Project Superintendent, Fran Giuffre, fran.giuffre@valentibuilders.com
City of Evanston
Evanston 311
Division of Engineering, Pelayo Enerio Jr. (Jhun), ph: (847) 448-4311
Thursday, October 2, 2014
Update 10/02/2014
ComEd will be on site the week of October 8, 2014 to
relocate their overhead facilities underground. AT&T cable TV service
may experiences short outages during this work.
Subscribe to:
Posts (Atom)