Thursday, October 29, 2015

Update October 29, 2015

The concrete structure is complete. Installation of the perimeter framing, sheathing, insulation and weather barrier has started and is 60% complete. Brick work will start by November 6th. Mechanical rough in has started in the interior of the building.