Thursday, October 29, 2015

Update October 29, 2015

The concrete structure is complete. Installation of the perimeter framing, sheathing, insulation and weather barrier has started and is 60% complete. Brick work will start by November 6th. Mechanical rough in has started in the interior of the building.

Thursday, June 11, 2015

Update June 11, 2015

All deep grade beams and basement foundations are complete. The shallow east side grade beams are complete with 8 first floor columns. The shallow west side grade beams will start week of 6/15/15. There will be no revisions to the construction barricades in the near future.

Wednesday, March 25, 2015

Update March 25, 2015

The caissons, sheeting and excavation for the basement are complete. Concrete began being poured the week of March 23rd. The basement foundations and grade beams will be worked on for the next few months.