The concrete structure is
complete. Installation of the perimeter framing, sheathing, insulation and
weather barrier has started and is 60% complete. Brick work will start by
November 6th. Mechanical rough in has started in the interior of the
building.
Updates for the construction work being performed at 1619 Chicago Avenue in Evanston, Illinois.
Thursday, October 29, 2015
Thursday, June 11, 2015
Update June 11, 2015
All deep grade beams and
basement foundations are complete. The shallow east side grade beams are
complete with 8 first floor columns. The shallow west side grade beams will
start week of 6/15/15. There will be no revisions to the construction
barricades in the near future.
Wednesday, March 25, 2015
Update March 25, 2015
The caissons, sheeting and excavation for the basement are complete. Concrete began being poured the week of March 23rd. The basement foundations and grade beams will be worked on for the next few months.
Subscribe to:
Posts (Atom)