Wednesday, November 19, 2014

Update November 19, 2014

Site Demolition work is complete. Foundation and Caisson will begin this week and continue through mid December.

Monday, October 27, 2014

Update October 27, 2014

Installation of temporary fencing around the perimeter of the construction site will commence the week of October 27th followed by minor site demolition, earth retention, and foundation construction. The site will be set up using the East traffic lane, curb lane and sidewalk in front of the property for both site access and a pedestrian walkway to maintain pedestrian traffic along the East side of Chicago Avenue during the duration of the construction project.  Site demolition and foundation work will commence in early November and will continue through December 2014.  

Wednesday, October 8, 2014

Project Contacts

Valenti Builders
Project Executive, Bob Weber, ph: (847) 716-7226, email: bob.weber@valentibuilders.com
Project Superintendent, Fran Giuffre, fran.giuffre@valentibuilders.com

City of Evanston
Evanston 311
Division of Engineering, Pelayo Enerio Jr. (Jhun), ph: (847) 448-4311

Thursday, October 2, 2014

Update 10/02/2014

ComEd will be on site the week of October 8, 2014 to relocate their overhead facilities underground.  AT&T cable TV service may experiences short outages during this work.